University Campus Suffolk, Ipswich, Suffolk, IP4 1QJ- Temporary Electrical Installation to site works area.

Tom Bonner - Friday, July 24, 2015

Installation, Commissioning and Testing of Temporary Electrical Installation serving welfare areas.

Installation, Commissioning and Testing of 2no Temporary MDU Panels to site works areas.

Installation, Commissioning and Testing of 10no 10kVA transformer boxes to site works areas. Ongoing

Great Ormond Street, London, WC1 W1DZ- Emergency Callout- Loss of electrical services.

Tom Bonner - Monday, July 13, 2015

Emergency callout during out of hours, to inspect damage to severed LV Mains supply cabling feeding floor distribution board.

Damaged cabling made safe and 1no new LV supply installed between switchroom and Ground Floor Intake room. Completed

Wingate Rd, Sidcup, DA14 6SH- Temporary Electrical Installation to site works area

Tom Bonner - Tuesday, June 23, 2015

Installation, Commissioning and Testing of Temporary Electrical Installation serving welfare areas.

9no Transportable buildings and site compound.

Including installation of permanent LV electrical supplies for security and lighting setups. Completed

Romney Marsh, Kent- Dungeness 'A' Power Station- Temporary Electrical Installation To Radiological Controlled Area.

Tom Bonner - Tuesday, June 23, 2015

Installation, Commissioning and Testing of Temporary Electrical Distribution feeding Demolition Works area. 

Installation of 14no 10kVA 400V Transformer final circuits fed via 250kVA Generator supplying Demolition Works area. Ongoing


Romney Marsh, Kent- Dungeness 'A' Power Station- Turbine Hall Pump Control Electrical Installation

Tom Bonner - Wednesday, June 17, 2015

Installation of suspended 300m galvanised tray work system serving 2no Pump Control Circuits. Completed 

Installation/Testing/Commissioning of 2no Direct-On-Line Starter Pump Control systems. Completed

Stoke-on-Trent, Staffordshire- Major Retailer- Asbestos Enclosure Works

Tom Bonner - Sunday, May 03, 2015

LV Circuit isolations and alterations. Out of Hours within Asbestos Enclosure. Ongoing

Romford,Essex- Rewire 3 Bed Residential Dwelling

Tom Bonner - Sunday, May 03, 2015

Complete electrical rewire of all circuits, including installation of new Gas/Water Main bonding conductors and Consumer Unit. Completed

Essex- EICR (Periodic) Inspection and Certification

Tom Bonner - Sunday, May 03, 2015

Completion of EICRs and related remedial works. Landlord owned dwellings. Ongoing

Romney Marsh, Kent- Dungeness 'A' Power Station- Temporary Electrical Installation to site works area.

Tom Bonner - Sunday, May 03, 2015

Installation, Commissioning and Testing of temporary electrical installation supplying site welfare area . Completed